Painting : industrial rope access vs. scaffolding
Client: Municipal swimming pool, St. Pieters Woluwe, Brussels, Belgium
For: Group Baeck Jansen
                                                     View next case study



The brief was as follows:
 
Paint repairs and corrections
  working from snag-list to new
  roof and support structure of
  swimming pool.

 
Options: Scaffolding, Rope Access or Cradle
                TASK

Scaffolding

Capaxis

Cradles

Erection
60 hours
    Setup
1 hours
   Set up
12 hours

Task

230 hours
   Task 160 hours
   Task
205 hours

Dismantle


36 hours


    Clear


1 hours


   Dismantle


8 hours


     TOTAL:            326 hours

162 hours       

235 hours



Value of rope access vs. scaffolding
Traditionally a task involving scaffolding, the table demonstrates how these other forms of access can gain the client flexibility and savings.

Value of rope access vs. cradles
Even mobile platforms require a measure of installation - industrial abseiling does not.