The brief was as follows:
 
Full visual and photo survey
Pull and fix cabling for measuring
  equipment

 
Options: Scaffolding or Rope Access
TASK
Scaffolding
  Erection 34 hours
  Task 50 hours
  Dismantle 21 hour
Capaxis
  Set up 4 hours
  Task 60 hours
  Clear 1 hour

TOTAL
105 hours
65 hours

This is a saving of over 35% in time and time is money!
 
Value
This was a relatively simple task, but was within the production site. We were able to successfully complete our tasks whilst allowing operations to continue without interruption.

Not only does rope access not require a large ground footprint (unlike scaffolding), but our ability to complete the contract with minimum of disturbance was another key factor. Mobile platforms were excluded due to their inability to get between the silos and ducting.

We were more effective in every way than the alternatives, and our speed of response has no rival.
 
"You are the first rope access company that has satisfied our safety conditions, and that has been allowed to work on this site."
 
Client to the Team Supervisor.


Consult our references or contact us directly for a no-obligation consultation and see for yourself how industrial rope access can be the solution you are looking for!
 